In the last few weeks since july 12th, the second built "Giruno" RABe 501 # 002 from Stadler Rail for the SBB, was equipped with a large amount of sensors, wiring and measuring divices. This train... (more)
The second train of the new "Giruno" type RABe 501 # 002 from Stadler Rail for the SBB made the first brake test runs on the Thur valley mainline between Sulgen and Romanshorn this day. ... (more)
On this day, the second "Giruno" highspeed train for the SBB, RABe 501 # 002, made it's first brake test runs on the Thur valley mainline between Sulgen and Romanshorn. When the train left the Sta... (more)
On this day, the second "Giruno" highspeed train RABe 501 # 002 for the SBB left the Stadler Rail commissioning centre Erlen (IBS) for the very first time, to make some brake test runs on the Thur... (more)
Transport of three cars for the new GIRUNO RABe 501 # 002 highspeed train for the SBB, from Stadler Rail's Bussnang plant to the commissioning center Erlen, loaded on 4 lowfloor freight cars.