With heavy equipment from the Heartland Corridor project parked about, coal drag S0N crawls west out of Vaughn Tunnel. Work has progressed inside with the roof being raised and notched.
NS 759 takes coal mtys to Hull for loading at Litwar Processing. Note the test drill holes above the portal for the Heartland Corridor project, which will soon raise the roof of the tunnel.
Clouds of dust and rock are kicked up by a westbound at Roderfield tunnel, evidence of heavy tunnel work inside. The Heartland Corridor project is advancing quickly over the Pokey.
An eastbound 194 pops out of Laurel Tunnel, showing the signs of the Heartland Corridor project around the arch. The tunnel will be notched and the ceiling raised as high as the marks shown.